Downtown Line
From SgWiki
The Downtown Line (DTL) will be built in three stages, with Stage 1 to be completed in 2013, Stage 2 to be completed in 2015 and Stage 3 in 2017. When fully completed, the DTL will enhance the connectivity of the Rapid Transit System network and facilitates direct travel from the northwestern and eastern areas of the island to the Central Business District and the Marina Bay.
Contents |
Stage 1
The 4.3km Line comprises 6 stations. These stations are: Chinatown, Telok Ayer, Downtown, Bayfront, Promenade and Bugis. It will feature 4 Interchanges, with links to North East Line (NEL), East West Line (EWL) and Circle Line (CCL). Stage 1 of the Line has commenced its construction in 2009 and will be completed in 2013 and will provide a strategic transport link to serve workers, residents and visitors in the exciting Marina Bay area and upcoming developments such as the Marina Bay Sands Integrated Resorts and the Marina Bay Financial Centre.
- Chinatown Interchange Station (Interchange for DTL2 and NEL)
牛车水转换站 (滨海市区线第1阶段和东北线转换站) - Telok Ayer Station
直落亚逸站 - Downtown Station
市中心站 - Bayfront Interchange Station (Interchange for DTL2 and CCL Marina Bay Extension)
海湾转换站 (滨海市区线第1阶段和环线滨海湾延长转换站) - Promenade Interchange Station (Interchange for DTL2 and CCL)
宝门廊转换站 (滨海市区线第1阶段和环线转换站) - Bugis Interchange Station (Interchange for DTL2 and EWL)
武吉士转换站 (滨海市区线第1阶段和东西线转换站)
Stage 2
The 16.6km long Downtown Line Stage 2 (DTL2) comprises one depot and 12 stations, including three interchange stations at Little India, Newton and the Botanic Gardens. These 3 interchange stations will link to the North East Line(NEL), North South Line(NSL) and Circle Line(CCL) respectively, giving commuters greater accessibility to the rest of the island and significantly improving travel time.
- Rochor Interchange Station
梧槽转换站 - Little India Station (Interchange for DTL2 and NEL)
小印度转换站 (滨海市区线第2阶段和东北线转换站) - Newton Station (Interchange for DTL2 and NSL)
纽顿转换站 (滨海市区线第2阶段和南北线转换站) - Stevens Station
史蒂芬站 - Botanic Gardens (Interchange for DTL2 and CCL)
植物园转换站 (滨海市区线第2阶段和环线转换站) - Tan Kah Kee Station
陈嘉庚站 - Sixth Avenue Station
第六道站 - King Albert Park Station
阿尔柏王园站 - Beauty World Station
美世界站 - Hillview Station
山景站 - Cashew Station
凯秀站 - Bukit Panjang Station
武吉班让站
Stage 3
The 19.1km Line will feature 16 stations. It will run through MacPherson, Bedok Reservoir and Tampines ending at the East West Line Expo Station. Scheduled to be completed in 2017, it will reduce travel time by 10 minutes for commuters traveling to the city from Bedok Reservoir and Tampines. It will feature 3 Interchanges, with links to East West Line (EWL), Changi Airport Extension Line (CGL) and Circle Line (CCL).
Stage 3 of the Downtown Line is the final stage and as of 20 August, LTA confirmed the following stations:
- River Valley (Working name)
- Bencoolen (Working name)
- Sungei Road (Working name)
- Jalan Besar (Working name)
- Kallang Bahru (Working name)
- Mattar (Working name)
- MacPherson Interchange Station (Interchange for DTL2 and CCL)
麦波申转换站 (滨海市区线第3阶段和环线转换站) - Ubi (Working name)
- Kaki Bukit (Working name)
- Bedok Town Park (Working name)
- Bedok Reservoir (Working name)
- Tampines West (Working name)
- Tampines Interchange Station (Interchange for DTL3 and EWL)
淡滨尼转换站 (滨海市区线第3阶段和东西线转换站) - tampines East (Working name)
- Upper Changi (Working name)
- Expo Interchange Station (Interchange for DTL3 and CGL)
博览转换站 (滨海市区线第3阶段和樟宜机场延长线转换站)
Stations
| Alpha-Numeric Code | Abbreviation | Station Name | Notes | |||
|---|---|---|---|---|---|---|
| English | Chinese | Tamil | ||||
| Downtown Line | ||||||
| DT1 / BP6 | BPJ | Bukit Panjang | 武吉班让 | புக்கிட் பாஞ்சாங் | U/C, Terminus (11), Future Interchange station with BPLRT | |
| DT2 | Unknown | Cashew | 凯秀 | U/C | ||
| DT3 | Unknown | Hillview | 山景 | U/C | ||
| DT4 | (Future Station at Hume Avenue) | |||||
| DT5 | Unknown | Beauty World | 美世界 | U/C | ||
| DT6 | Unknown | King Albert Park | 阿尔伯王园 | U/C | ||
| DT7 | Unknown | Sixth Avenue | 第六道 | U/C | ||
| DT8 | Unknown | Tan Kah Kee | 陈嘉庚 | U/C | ||
| DT9 / CC19 | BTN | Botanic Gardens | 植物园 | U/C, Future Interchange station with CCL | ||
| DT10 | Unknown | Stevens | 史蒂芬 | U/C | ||
| DT11 / NS21 | NEW | Newton | 纽顿 | நியூட்டன் | U/C, Future Interchange station with NSL | |
| DT12 / NE7 | LTI | Little India | 小印度 | லிட்டில் இந்தியா | U/C, Future Interchange station with NEL | |
| DT13 / DT22 | Unknown | Rochor | 梧槽 | U/C, Latest plans had showed that it will NOT interchange with Downtown Line Stage 3 | ||
| DT14 / EW12 | BGS | Bugis | 武吉士 | பூகிஸ் | U/C, Terminus (11) until completetion of DTL2, Future Interchange station with EWL | |
| DT15 / CC4 | PMD | Promenade | 宝门廊 | U/C, Future Interchange station with CCL | ||
| DT16 / CE1 | Unknown | Bayfront | 海湾 | U/C | ||
| DT17 | Unknown | Downtown | 市中心 | U/C | ||
| DT18 | Unknown | Telok Ayer | 直落亚逸 | U/C | ||
| DT19 / NE4 | CNT | Chinatown | 牛车水 | சைனாடவுன் | U/C, Terminus (12) until completetion of DTL3, Future Interchange station with NEL | |
| DT20 | Unknown | River Valley | 里峇峇利 | ?? | ||
| DT21 | Unknown | Bencoolen | 明古连 | ?? | ||
| DT22 | Unknown | Sungei Road | 双溪路 | ?? | U/C | |
| DT23 | Unknown | Jalan Besar | 惹兰勿刹 | ?? | U/C | |
| DT24 | Unknown | Kallang Bahru | 加冷峇鲁 | ?? | U/C | |
| DT25 | Unknown | Mattar | 玛达 | ?? | U/C | |
| DT26 / CC10 | Unknown | MacPherson | 麦波申 | U/C, Future Interchange station with CCL | ||
| DT27 | UBI | Ubi | 乌美 | ?? | U/C | |
| DT28 | Unknown | Kaki Bukit | 加基武吉 | ?? | U/C | |
| DT29 | Unknown | Bedok Town Park | 勿洛镇公园 | ?? | U/C | |
| DT30 | Unknown | Bedok Reservoir | 勿洛水池 | ?? | U/C | |
| DT31 | Unknown | Tampines West | 淡滨尼西 | ?? | U/C | |
| DT32 / EW2 | TAM | Tampines | 淡滨尼 | தெம்பினிஸ் | U/C, Future Interchange station with EWL | |
| DT33 | Unknown | Tampines East | 淡滨尼东 | ?? | U/C | |
| DT34 | Unknown | Upper Changi | 樟宜上段 | ?? | U/C | |
| DT35 / CG1 | XPO | Expo | 博览 | எக்ஸ்போ | U/C, Terminus (12), Future Interchange station with CGL | |
Note :
- Construction for the Downtown Line Stages 1 & 2(DTL) has begun. Its schematic profile, station names as well as alpha-numeric and end-destination codes are subject to confirmation.
Newsletters
- DTL1 Issue 1 : English / Mandarin
- DTL1 Issue 2 : English / Mandarin
- DTL1 Issue 3 : English and Mandarin
- DTL1 Issue 4 : English and Mandarin
- DTL1 Issue 5 : English and Mandarin
- DTL1 Issue 6 : English and Mandarin
- DTL1 Issue 7 : English and Mandarin
- DTL1 Issue 8 : English and Mandarin
- DTL1 Issue 9 : English and Mandarin
Category Links
| Mass Rapid Transit (Singapore) | ||
|---|---|---|
| Lines and stations | Current | North South Line • East West Line • Changi Airport Extension • North East Line • Circle Line |
| Under Construction | Circle Line • Marina Bay Extension • Downtown Line • Thomson Line • Eastern Region Line | |
| Future | Thomson Line • Eastern Region Line | |
| Defunct | Branch Line | |
| Rolling stock | Kawasaki Heavy Industries C151 • Siemens C651 • Kawasaki Heavy Industries & Nippon Sharyo C751B • Alstom Metropolis C751A • Alstom Metropolis C830 • Kawasaki Heavy Industries C151A • Bombardier MOVIA C951 | |
| Depots | Bishan • Changi • Gali Batu • Kim Chuan • Sengkang • Ulu Pandan | |